Following parts of ordinary bolt connection: wall-beams, purlins, knee. Design of drainage, electrical, heating, ventilation, air conditioning, power should be subject to safety requirements for steel structures of other professions, it is forbidden to weld hanging load and increased roof and columns. Construction prepared and the construction layout first section material prepared and the processing production prepared according to Zhejiang more Palace steel limited and Wuhan intelligent elevator limited by signed of contract file and the Institute provides of steel design blueprint, I company and the Organization Technology Department, production department, procurement Department, bid do Engineering Department, related production sector for drawings triage, and according to owners requirements timely design out production and the processing detail and for has related professional sector of strictly triage, specific work prcess following: Bid do bid notice → echnology Department → add up do → procurement department → production department → quality Dpartment → Engineering Department Technology Department production and the processing detail proposed Hou, by add up do coordination the sector of supporting work, and by figure line by varieties, and specifications, and quality for classified, and notification Procurement Department for material of market survey and procurement, by quality Department according to by purchased material of specifications varieties for quality review and test, not qualified of material varieties and specifications strongly ban for the engineering in the, After passing inspection informed the workshop of production of timber according to strict production details of production, workshop organized by the General Manager before the production technology and security sector technical safety training, safety education company to strictly three-level disclosure, training of qualified personnel is strictly prohibited to post production, production personnel must be listed to work, you must have the corresponding certificate. Road workers must have the certificate, and regular assessments should be carried out, not a skilled operator posts is strictly prohibited. Production of various items of equipment, appliances and other, non-professional is strictly prohibited actions and strict regulations, strong rewards, be eliminated. Production line set on person, title, responsibilities, and performance and safety comprehensive assessment. Material procurement process strictly handling the《建筑工程计量与计价》复习思考题

1、建设项目根据其组成可依次划分为:单项工程、单位工程、分部工程和分项工程,并能区分及举例说明。 2、现浇钢筋混凝土柱、梁、板工程量如何计算。

3、现浇钢筋混凝土整体楼梯包括哪些部分,工程量如何计算。 4、现浇混凝土构件的模板工程量如何计算。 5、现浇混凝土台阶工程量如何计算。

6、设计无规定时,女儿墙泛水弯起部分工程量如何计算。 7、外墙面抹灰工程量如何计算。

8、在楼地面工程中,整体面层工程量如何计算。 9、内、外墙脚手架工程量如何计算。 10、满堂脚手架工程量如何计算。 11、民用建筑的类别如何划分?

有两个指标:层数和建筑面积;二类建筑8-12层、8000-12000m2;三类建筑8层以下、8000 m2以下。 12、清单计价与定额计价有什么联系与区别。

1)计价依据不同。这是清单计价和按定额计价的最根本区别。按定额计价的唯一依据就是定额,而工程量清单计价的主要依据是企业定额。

2)单位工程造价构成形式有差别。按定额计价时单位工程造价由直接工程费、间接费、利润、税金构成,工程量清单计价时,造价由工程量清单费用(=∑清单工程量×项目综合单价)、措施项目清单费用、其他项目清单费用、规费、税金五部分构成。

3)单位工程项目划分有差异。按定额计价的工程项目划分即预算定额中的项目划分,一般土建定额有几千个项目,工程量清单计价的工程项目划分较之定额项目的划分有较大的综合性,它考虑工程部位、材料、工艺特征,但不考虑具体的施工方法或措施。

13、直接工程费由哪几项组成?熟悉各部分由哪些费用组成。

14、分部分项工程量清单中的编码由几级组成和多少位数字组成,每一级编码各表示什么? 15、建筑工程分部分项清单项目包括哪几个章节的内容? 16、工程量清单计价模式下的建筑安装工程费用由哪几部分组成?

分部分项工程费、措施项目费、其它费用、规费、税金。 17、工程建设程序中各阶段应相应做出何种计价?

Following parts of ordinary bolt connection: wall-beams, purlins, knee. Design of drainage, electrical, heating, ventilation, air conditioning, power should be subject to safety requirements for steel structures of other professions, it is forbidden to weld hanging load and increased roof and columns. Construction prepared and the construction layout first section material prepared and the processing production prepared according to Zhejiang more Palace steel limited and Wuhan intelligent elevator limited by signed of contract file and the Institute provides of steel design blueprint, I company and the Organization Technology Department, production department, procurement Department, bid do Engineering Department, related production sector for drawings triage, and according to owners requirements timely design out production and the processing detail and for has related professional sector of strictly triage, specific work process following: Bid do bid notie → echnology Department → add up do → procurement department → production department → quality Department → Engineering Departmenechnology Department production and the processing detail proposed Hou, by add up do coordination the sector of supporting work, and by figure line by varieties, and specifications, and quality for classified, and notification Procurement Department for material of market survey and procurement, by quality Department according to by purchased material of specifications varieties for quality review and test, not qualified of material varieties and specifications strongly ban for the engineering in the, After passing inspection informed the workshop of production of timber according to strict production details of production, workshop organized by the General Manager before the production technology and security sector technical safety training, safety education company to strictly three-level disclosure, training of qualified personnel is strictly prohibited to post production, production personnel must be listed to work, you must have the corresponding certificate. Road workers must have the certificate, and regular assessments should be carried out, not a skilled operator posts is strictly prohibited. Production of various itemof equipment, appliances and other, non-professional is strictly prohibited actions and strict regulations, strong rewards, be eliminated. Production line set on person, title, responsibilities, and performance and safety comprehensive assessment. Material procurement process strictly handling the

计算题:

1、已知某工程钢筋混凝土条形基础的平面图和剖面图如下图所示,土壤类型为二类土。试编制挖基础土方的清单。(清单编码:)

解:条形基础长=(3.5*2+3.3*2)*2+(3.5-0.6*2)+

(3.3*2-0.6*2)=34.9M 挖土深度=1.65-0.45=1.2M

挖土方工程量=条形基础长*垫层宽*挖土深度 =34.9*1.2*1.2 =50.256M^3

序号 项目编码 项目名称 计量单位 工程量 1 1 挖基础土方 M^3 50.256

Following parts of ordinary bolt connection: wall-beams, purlins, knee. Design of drainage, electrical, heating, ventilation, air conditioning, power should be subject to safety requirements for steel structures of other professions, it is forbidden to weld hanging load and increased roof and columns. Construction prepared and the construction layout first section material prepared and the processing production prepared according to Zhejiang more Palace steel limited and Wuhan intelligent elevator limited by signed of contract file and the Institute provides of steel design blueprint, I company and the Organization Technology Department, production department, procurement Department, bid do Engineering Department, related production sector for drawings triage, and according to owners requirements timely design out production and the processng detail and for has related professional sector of strictly triage, specific work process following: Bid do bid notice → echnology Department → add up do → procurement department → production department → quality Department → Engineering Department echnology Department production and the processing detail proposed Hou, by add up do coordination the sector of supporting work, and by figure line by varieties, and specifications, and quality for classified, and notification Procurement Department for material of market survey and procurement, by quality Department according to by purchased material of specifications varieties for quality review and test, not qualified of material varieties and specifications strongly ban for the engineering in the, After passing inspection informed the workshop of production of timber according to strict production details of production, workshop organized by the General Manager before the production technology and security sector technical safety training, safety education company to strictly three-level disclosure, training of qualified personnel is strictly prohibited to post production, production personnel must be listed to work, you must have the corresponding certificate. Road workers must have the certificate, and regular assessments should be carried out, not a skilled operator posts is strictly prohibited. Production of various items of equipment, appliances and other, non-professional is strictly prohibited actions and strict regulations, strong rewards, be eliminated. Production line set on person, title, responsibilities, and performance and safety comprehensive assessment. Material procurement process strictly handling the

2、如图所示,带形钢筋混凝土基础平面图,试按断面1-1所示的情况计算工程量,并编制工程量清单。(清单编码:)

解:外墙长=(3.6*2+4.8)*2=24M 内墙长=4.8-0.5*2=3.8M

带型基础长=外墙长+内墙长=24+3.8=27.8M

带型基础工程量=带型基础长*带型基础的截面面积 =27.8*1*0.3 =8.34M^3

序号 项目编码 项目名称 计量单位 工程量 1 1 现浇混凝土 M^3 8.34 带型基础

3、如下图,某项目地面铺贴大理石面层,平面尺寸如下图,楼地面做法是素土夯实,100厚3:7灰土垫层,50厚素混凝土基层,素水泥浆结合层,干硬性水泥砂浆找平层,大理石板面层,试计算工程量,编制该项目清单。(清单编码:)

Following parts of ordinary bolt connection: wall-beams, purlins, knee. Design of drainage, electrical, heating, ventilation, air conditioning, power should be subject to safety requirements for steel structures of other professions, it is forbidden to weld hanging load and increased roof and columns. Construction prepared and the construction layout first section material prepared and the processing production prepared according to Zhejiang more Palace steel limited and Wuhan intelligent elevator limited by signed of contract file and the Institute provides of steel design blueprint, I company and the Organization Technology Department, production department, procurement Department, bid do Engineering Department, related production sector for drawings triage, and according to owners requirements timely design out production and the processing detail and for has related professional sector of strictly triage, specific work process following: Bid do bid notie → echnology Department → add up do → procurement department → production department → quality Department → Engineering Departmenechnology Department production and the processing detail proposed Hou, by add up do coordination the sector of supporting work, and by figure line by varieties, and specifications, and quality for classified, and notification Procurement Department for material of market survey and procurement, by quality Department according to by purchased material of specifications varieties for quality review and test, not qualified of material varieties and specifications strongly ban for the engineering in the, After passing inspection informed the workshop of production of timber according to strict production details of production, workshop organized by the General Manager before the production technology and security sector technical safety training, safety education company to strictly three-level disclosure, training of qualified personnel is strictly prohibited to post production, production personnel must be listed to work, you must have the corresponding certificate. Road workers must have the certificate, and regular assessments should be carried out, not a skilled operator posts is strictly prohibited. Production of various itemof equipment, appliances and other, non-professional is strictly prohibited actions and strict regulations, strong rewards, be eliminated. Production line set on person, title, responsibilities, and performance and safety comprehensive assessment. Material procurement process strictly handling the

解:(1)--(2):(5.4-0.12*2)*(3.6*2-0.12*2)=35.9136M^2 (2)—(3):(5.4-0.12*2)*(3.6-0.12*2)*2=34.6752M^2 大理石面层工程量=(1)--(2)+(2)--(3) =35.9136+34.6752 =70.589M^2

序号 项目编码 项目名称 计量单位 工程量 1 1 石材楼地面 M^2 70.589

4、如图所示,外墙面为95X95灰色面砖(使用粘接剂粘贴面砖,墙面灰缝5mm以内),采用1:3水泥砂浆找平层,门窗尺寸分别为:M-1:900mm×2000mm;M-2:1200mm×2000mm;M-3:1000mm×2000mm;C-1:1500mm×1800mm;C-2:1800mm×1500mm;C-3:2700mm×1500mm。试计算外墙面抹灰工程量,并编制工程量清单。(块料墙面:,不需要描述清单项目特征)

解:外墙周长=【(3.9+5.1+0.24)+(3*2+0.24)】*2=30.96M 外墙高度=3.6+0.3=3.9M

门窗面积= M-1 + M-2 + C-1 + C-2 + C-3 =0.9*2 +1.2*2 + 1.5*1.8*4 +1.8*1.5 +2.7*1.5 =21.75M^2

抹灰工程量=外墙周长*外墙高度-门窗面积 =30.96*3.9-21.75

  • 收藏
  • 违规举报
  • 版权认领
下载文档10.00 元 加入VIP免费下载
推荐下载
本文作者:...

共分享92篇相关文档

文档简介:

Following parts of ordinary bolt connection: wall-beams, purlins, knee. Design of drainage, electrical, heating, ventilation, air conditioning, power should be subject to safety requirements for steel structures of other professions, it is forbidden to weld hanging load and increased roof and columns. Construction prepared and the construction layout first section material prepared and the proc

× 游客快捷下载通道(下载后可以自由复制和排版)
单篇付费下载
限时特价:10 元/份 原价:20元
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:fanwen365 QQ:370150219
Copyright © 云题海 All Rights Reserved. 苏ICP备16052595号-3 网站地图 客服QQ:370150219 邮箱:370150219@qq.com