1. Task / Objective 目的
- Long-term monitoring of the production-processes.
生产过程的长期监督。
2. Scope of Application 范围
- avim Solar Production Co. Ltd; Gaomi / China;
埃孚光伏制造有限公司;高密/中国;
3. Definitions 术语和定义
Damp-Heat Test: Long-term inspection for evaluating the durability of photovoltaic-modules against influences by atmospheric-humidity and temperature. 湿热测试 评估光伏组件的耐久性即大气湿度和温度对组件的影响的长期检测。
4. Responsibilities 职责
- The QMS dept is responsible for selecting a module and to coordinate the damp-heat-test with the test-institute.
品保部负责挑选测试组件,送往测试机构进行湿热测试。
- The authorized test-institution is the VDE and the Local Test- institution or company who has the capacity to
conduct this test according to the requirements and procedure in IEC61215 and certified according to IEC17025.
授权测试机构为VDE和通过IEC17025认证并且有能力根据IEC61215的要求和流程进行这个测试的本地检测机构或公司。
5. Description 描述
5.1 Scope of Inspection and Frequency of Inspection检测范围和检测周期
- Two times per year a module has to be taken randomly out of one of the production lines.
每年两次,任选一条生产线随机挑选任一组件。
- The module type and production-line must vary for each year.
组件类型和生产线每年要有所不同。
- One module is selected in the first half year another module is selected in the second half year,the time
difference between two selections has to be at least 5 months.
上半年选择一次组件,另一次在下半年选择,两次选择时间差最少是5个月。
Document 文件 Name: 姓名 Date: 日期 Signature: 签名 Drawn by: 编制 Gao Peng 高鹏 2011.5.5 Original signed 原件签名 Checked by Department Manager: 部门经理审核 Checked by Document Manager: 文件管理员审核 Tian Kai 田凯 2011.5.5 Original signed 原件签名 Approved by DGM 副总经理批准 Stephan Czerwonka 陈泰房 2011.5.5 Original signed 原件签名 Approved by GM 总经理批准 Wu Mingfeng 吴明凤 2011.5.5 Original signed 原件签名 Volker.Viohl 杨光 2011.5.5 Original signed 原件签名 II-823-QMS-02 01 avim solar production Co.,Ltd,Gaomi (China) Damp Heat Test 湿热测试指导 Monitoring and Measurement of Processes 过程的监视和测量 No. of issue: 版本号: date of issue: 发行日期: page: 页码: 2 01 2011.5.5 of: 总页数 2 II-823-QMS-02 5.2 From this two tests, one test is done by VDE, another test is done by the Local Test- institution or company
who has the capacity to conduct this test according to the requirements and procedure in IEC61215 and certified according to IEC17025.
这两次测试,一次测试由VDE来做,另一次由通过IEC17025认证并且有能力根据IEC61215的要求和流程进行这个测试的本地检测机构或公司来做。
6. Applicable Documents and Records 相关文件和记录
- None
无
7. Documentation 文件存档
- The inspection-results are to be stored by the Quality-Management in digital- or paper-form.
品保部负责保存检测结果,以电子版或纸版。
- The inspection-results must be archived for a period of 20 years.
检测结果要求存档期限为20年。
8. Modifications 修订
- Due to changing the document layout,this document is considered as “first edition”.
因为更换文件格式,这个文件被当作初版。
- Topic 4 Adding the new authorized Testing-institution or company for damp heat test.
主题4 增加了新的被授权进行湿热试验的检测机构或公司。 - Topic 5.1 Changing the testing times for damp heat test
主题5.1 更改了湿热试验的测试次数,
- Topic 5.1 Adding the time requirement for two selections of modules
主题5.1 增加了两次选择组件的时间要求
- Topic 5.2 Specify that which test should be done by which test institution or company
主题5.2 明确了哪次测试由哪个测试结构或公司来做。
9. Appendices 附件
- None
无