石膏板贴面墙施工方法陈述 Method statement of Wall Veneering with Gypsum Boards Plant: PP+HDPE Client: CSPC 编号Ref.No: NH- HDPE+PP-WPR-292 Contractor: TISA Subcontractor: CP6CC REV:A Page 1 of 3 1. 适用范围:Scope
中国石油天然气第六建设公司承建的中海壳牌南海石化项目PP-HDPE 装置内的建筑物工程。
This procedure is applicable to buildings on HDPE/PP Plant, project contracted by CP6CC, for CSPC Nanhai Petrochemical Project. 2. 工艺流程: Work Flow
3. 施工方法Construction Methods 1) 施工准备 Preparations
根据图纸做法要求进行材料采购,提前进行材料报检;根据施工相关规范及材料厂家使用说明编制施工作业指导书,并对班组进行技术交底和现场指导与检查。
Purchase materials according to drawings and submit them for approval in advance. Prepare Work Instruction as per relevant construction codes and Material Specifications, and make a technical presentation and site instruction & inspection to construction team. 2) 墙面清理 Wall Cleaning
对墙面凹凸不平处进行修补和剔凿,铲除流坠的砂浆,对对拉螺栓的孔洞进行填塞。
Chip off or repair by plastering the rough points, brush out the falling mortar and fill
Preparations Wall Cleaning Line snapping Keel installation 施工准备 墙面清理 弹龙骨网格线 龙骨安装 面板安装 拼缝修补 耐水腻子面层涂料 Faceplate Installation Joint repairing Waterproof putty filling Coating