中铁二十局集团有限公司青荣城际铁路工程QRZH-IV标 隧道监控量测实施方案
目 录
一.编制依据 ································································ 1 二.编制原则 ································································ 1
1.高效、适用原则 ······································································· 1 2.安全原则 ···················································································· 1 3.符合本单位技术水平的原则 ··················································· 2 三.适用范围 ································································ 2 四.工程概况 ································································ 2
1.隧道概况 ···················································································· 2 2.施工存在的风险 ······································································· 2 3.监控量测目的 ············································································ 2 4.监控量测手段 ············································································ 3 五.监控量测实施方案 ···················································· 4
1.组织机构、人员及设备 ··························································· 4 2.监控量测程序和项目 ······························································· 5 3.监控量测点布置及方法 ··························································· 6 4.监测数据的统计分析与信息反馈 ········································ 10 六.无尺渐测现场应用 ··················································· 11 七.监控量测工作制度 ·················································· 12 八 附件 ····································································· 11
表A开挖工作面地质状况记录表 ·············································· 11 表B 隧道净空变化量测记录表 ·················································· 13
1
中铁二十局集团有限公司青荣城际铁路工程QRZH-IV标 隧道监控量测实施方案
表C拱顶下沉量记录表 ······························································· 14 表C地表沉降观测原始记录表 ·················································· 15
2
中铁二十局集团有限公司青荣城际铁路工程QRZH-IV标 隧道监控量测实施方案
一.编制依据
1.青荣城际铁路招标文件及新建青岛至荣城铁路工程施工图; 2.青荣城际铁路Ⅳ标段指导性施工组织设计; 3.铁道部颁发的规范、规程、标准:
(1)《铁路隧道工程施工技术指南》(TZ204-2008); (2)《国家一、二等水准测量规范》(GB12897—2006); (3)《高速铁路工程测量规范》(TB10601-2009); (4)《工程测量规范》(GB50026-2007);
(4)《铁路工程设计防火规范》(TB10063-2007 J774-2008); (5)《铁路隧道超前地质预报技术指南》(铁建设[2008]105号)。 4.青荣城际铁路建设指挥部有关要求。
二.编制原则
1.高效、适用原则
监控量测是新奥法施工中不可缺少的一项技术内容,是监视围岩和支护稳定性的重要手段,是判断设计、施工是否正确合理的主要依据,是监视施工是否安全可靠的眼睛。为了更精确更迅速的了解围岩的动态变化,判定其稳定性,从而保证施工安全。
本方案的高效运行,能确保预报质量并有效的指导施工,适合本工程所有隧道。
2.安全原则
隧道施工中开挖形成后,必须立即喷射不小于4cm厚的混凝土及时封闭围岩作为初支初喷层,紧跟监控量测,监控量测应在开挖后2-4小时
1
中铁二十局集团有限公司青荣城际铁路工程QRZH-IV标 隧道监控量测实施方案
进行,否则工作人员不得进入掌子面作业。
本方案的操作实施要安全,并能指导安全施工。 3.符合本单位技术水平的原则
本方案拟投入的设备、实施人员均符合本单位现有水平,能确保方案顺利实施。
三.适用范围
适用于青荣城际铁路Ⅳ标段隧道监控量测。
四.工程概况
1.隧道概况
本标段共有隧道10座,总长度11.017Km。隧道全部位于山东省烟台市境内,地貌形态为剥蚀丘陵,地形高低起伏,部分地段冲沟发育,基岩大部分裸露。隧道穿越的地层岩性多为片岩、花岗岩、变质岩等,岩性变化较大。隧道概况表见下页。
2.施工存在的风险
根据设计图纸提供的地质资料,不难发现,本标段隧道施工中存在坍塌、冒顶、突水、突泥等风险。
3.监控量测目的
(1)通过监控量测了解各施工阶段地层与支护结构的动态变化,把握施工过程中结构所处的安全状态,判断围岩稳定性,支护、衬砌可靠性。
(2)用现场实测的结果弥补理论分析过程中存在的不足,并把监测结果反馈设计、指导施工,为修改施工方法、调整围岩级别、变更支护设计参数提供依据。
2