1.1工程简介 ............................................................. 1 1.2主要工程量 ........................................................... 1 1.3控制性工期 ........................................................... 1 1.4工程特点 ............................................................. 1 二、施工整体布置 ......................................................................................................................... 2 2.1施工道路 ............................................................. 2 2.2施工供电 ............................................................. 2 2.3施工用水 ............................................................. 3 2.4基坑排水 ............................................................. 3 2.5施工设备布置 ......................................................... 3 三、施工总进度计划 ..................................................................................................................... 3 3.1编制依据与原则 ....................................................... 3 3.2施工安排 ............................................................. 3 四、主体工程施工措施 ................................................................................................................. 4 4.1混凝土分层分块 ....................................................... 4 4.2模板工程 ............................................................. 1 4.3钢筋工程 ............................................................. 3 4.4伸缩缝、止水及施工缝 ................................................. 4 4.5混凝土浇筑施工 ....................................................... 5
4.5.1混凝土施工缝处理 ....................................................................................................... 5 4.5.2混凝土入仓方式 ........................................................................................................... 5 4.5.3铺料方法及平仓、振捣 ............................................................................................... 6 4.5.4二期混凝土施工 ........................................................................................................... 7 4.5.5 混凝土养护 .................................................................................................................. 8 4.5.6混凝土预制构件制作及安装 ....................................................................................... 8 4.5.7混凝土温度控制措施及防裂措施 ............................................................................... 8 4.5.8关键部位混凝土施工 ................................................................................................. 10 五、资源配置 ............................................................................................................................... 11 5.1机械设备及仪器投入 .................................................................................................... 11 5.2劳动力安排 .................................................................................................................... 12 六、质量控制与验收 ................................................................................................................... 13 6.1质量目标 ........................................................................................................................ 13 6.2质量控制 ........................................................................................................................ 13 6.3质量验收 ....................................................................................................................... 14 七、安全防护与文明施工 ........................................................................................................... 15 7.1安全防护 ....................................................................................................................... 15 7.2文明施工 ....................................................................................................................... 15
1
一、工程概况
1.1工程简介
东坪水电站河床式厂房位于左河道,装机4×18MW,主厂房布置顺水流方向由进水渠、拦污栅、进口检修闸门、主副厂房、下游防洪墙、出口检修闸门及尾水渠等部分组成,安装间位于主厂房的左侧。
本水电站水轮机为灯泡贯流式水轮机。厂房为两机一缝,施工缝面设一道止水,打毛或凿毛处理,伸缩缝设两道止水,沥青砂板填缝。1#机设检修集水井,2#机设渗漏集水井。
1.2主要工程量
厂房工程的土石方开挖量约14.44万m3,大体积的开挖已完成,局部欠挖正在处理。
厂房混凝土浇筑方量达11万m3,其中多为大体积混凝土,少数为二期混凝土及板、梁、柱结构混凝土。
厂房钢筋制安约4000T,帷幕及固结灌浆约1050m、三套发电机组的安装、厂房装饰装修等。
1.3控制性工期
根据本工程的合同条款及相关技术文件,厂房工程的控制性工期如下: 2006年03月31日,厂房封闭。 2006年12月26日,首台机组发电。
1.4工程特点
厂房工程是一期施工的重点,与一期溢流坝及重力坝同时进行施工,相
- 1 -
互间的施工干扰大。且混凝土浇筑与机组安装同时进行,增加了工作的难度。
厂房工程的混凝土工程量大(有相当数量的二期混凝土及小体积的板梁柱混凝土及预制混凝土),混凝土品种多工程项目多,工期紧。
模板工程量大,品种多,精度要求高。
预制模板的工作量大。对于胸墙、门槽、廊道、墩墙、牛腿、预制件等需单独设计模板、支撑、加固等结构型式。对于流道模板、门槽模板,在接口部位中心点的控制误差为3~5mm,结构表面的平整度控制误差为20mm。
由于受开挖等因素影响,目前施工进度已严重滞后导致混凝土浇筑施工强度较大。
厂房混凝土浇筑方量达11万m3,2006年06月15日厂房封顶,具备机组安装条件,高峰期混凝土月平均浇筑强度需达20000m3以上。大量的门槽、机组等二期混凝土浇筑部位钢筋布置密集,浇筑空间小,且有预埋件等,施工质量要求高,施工难度大。厂房的大部分混凝土安排在夏季施工,气温高,需对混凝土的温度进行严格控制,加强混凝土的养护措施,增加了工作的难度。
二、施工整体布置
2.1施工道路
厂房施工期间的混凝土、钢筋及原材料等运输依靠现有的施工道路,至施工现场运输由上下游下基坑道路承担,具体见厂房浇筑施工总布置图。
2.2施工供电
厂房上下游各布置一台250KVA变压器为上下游门机供电,施工照明及其它施工用电由营地前630KVA变压器供电。所有输电线路均采用水泥电杆架设。
2
2.3施工用水
施工用水主要已建成投入使用的400m3生产水池提供,供水主管为8吋管,支管为4吋管,至个施工工作面采用橡胶软管供水。
2.4基坑排水
下游侧布置一台55kw水泵作为厂房经常性排水设备,仓面冲洗、临时排水等根据实际需要配置3KW潜水泵排水,基坑排水最终经目前排水系统排出基坑。
2.5施工设备布置
一期施工基坑共布置有1#、2#、3#共3台门机,1#门机为高架圆筒门机,厂房上游门机为2#半高架门机,下游门机为低架门机,同时可使用履带吊协同运输混凝土入仓。施工设备布置具体位置及覆盖范围见《厂房浇筑施工总布置图》。
三、施工总进度计划
3.1编制依据与原则
根据本工程控制性节点工期的要求及目前的施工完成情况、厂房混凝土的分层分块图、混凝土温度控制要求,结合本工程施工特性及我部投入本工程施工的人力、物力及机械设备等,编制厂房工程的施工总进度计划。
3.2施工安排
根据枢纽总体布置、总体施工进度要求及目前的施工现状,厂房主体混凝土施工工期较紧,为加快工程施工进度,尽量多出工作面,同时考虑到基础的帷幕及固结灌浆,先安排厂房3#、4#机底板施工,厂房右侧施工先考虑