当前位置:首页 > 西藏某水电站厂房装修施工组织设计
西藏某电站厂房建筑与装修工 程
施工组织设计
二OO四年四月十一日
西藏某电站厂房建筑与装修 施工组织设计
目 录
1 2 2.1 2.2 3 4 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 5 5.1 5.2 5.3 6 7
工程概况 ······················································································ 3 材料的选择及管理 ·········································································· 3
材料的选择 ·············································································· 3 材料的管理 ·············································································· 3 主要机具设备 ················································································ 4 各项施工说明 ················································································ 4
装饰架子工程 ··········································································· 4 天棚抹灰工程施工 ····································································· 5 内墙面抹灰施工 ········································································ 5 地面花岗石和地砖施工 ······························································· 6 铝合金推拉窗的施工 ·································································· 8 瓷砖墙面安装作法 ····································································· 8 天棚工程 ················································································ 10 乳胶腻子面层施工 ···································································· 11 地面豆石地坪施工 ···································································· 11 墙面挂贴花岗石施工 ································································· 12
屋面工程的施工 ············································································ 12
水泥砂浆找平 ·········································································· 12 水泥膨胀珍珠岩找坡 ································································· 14 屋面4厚SBS改性沥青卷材防水层 ·············································· 15 质量控制措施 ··············································································· 16 工程施工进度安排 ········································································· 17
2
西藏某电站厂房建筑与装修 施工组织设计
1 工程概况
本工程是西藏某电站厂房装修工程,厂房由主、副厂房组成,总建筑面积约为6500m2。厂房外墙面粘贴乳白色饰面砖;主机间及安装间内墙面3.8米以下及地面贴花岗石。除花岗石及耐酸砖内墙面外,其余所有室内天棚、墙面都是以水泥砂浆抹灰为基础,面层刮腻子刷乳胶漆饰面。GIS楼地面及副厂房休息室、会议室及楼梯间铺贴地砖,中控室和通信室、通信设备室地面铺设防静电地板,其余所有楼地面及过道饰以水泥豆石地坪。中控室及通信室和通信设备室存在吊顶,以50型轻钢龙骨为龙骨架,埃特尼特板蒙面,乳胶漆饰面。门采用钢质防火门和铝合金平开门,窗户采用90型铝合金推拉窗,银白料绿玻。屋面为卷材防水屋面,卷材以SBS改性沥青卷材做防水,水泥膨胀珍珠岩做保温找坡层。
除厂房外,闸坝上的配电房、工具房、泄洪闸等项目和厂区绝缘油库,门卫室等项目亦参照本方案执行。
2 材料的选择及管理
2.1 材料的选择
装修工程水泥全部采用峨眉425#水泥,除外墙砖沟缝采用细砂外其余均采用中砂。装修材料如花岗石、外墙砖、室内地砖、耐酸砖、抗静电地板、埃特尼特板、卫生间墙砖,铝方板、铝合金窗型材、玻璃等,均由业主、设计、监理及施工单位共同采集样品,集体确定。施工单位按所封样品采购,各方按封样验收材料。
2.2 材料的管理
1、建立材料管理制度,材料员对原材料材质标准要严格把关,对原材料、成品和半成品先检验后收料,不合格的材料坚决不准进场。
2、原材料必须具备出厂合格证或法定检验单位出具的合格证明和材质证明书。水泥还应注明出厂日期、批号、数量和使用部位、品牌等,抄件应注明原件存放单位和抄件人、抄件时间并签章。
3、试验员对进场原材料应按规定进行复检的材料,及时送检,经检验不合格,不
3
西藏某电站厂房建筑与装修 施工组织设计
得使用。
4、各种不同类型、不同型号的材料分类堆放整齐,运输、存放时需保留标牌,按批量分类,并注意防锈蚀和污染。
3 主要机具设备
为满足施工需要,缩短工期,各施工阶段须配备足够的施工机具,并注意不同阶段机具的要求差别及有效衔接。本工程所需主要机具设备详表如下:
名 称 砂浆搅拌机 砼搅拌机 交流电焊机 型材切割机 冲击钻 电锤 空压机 电园锯 电刨 木工平刨机 高压水泵 手工提升架 水准仪 型号 JDT350 BX-330 MB106 80m扬程 N2 数量(台) 3 1 3 5 6 5 2 2 1 1 2 10 1 总功率(Kw/hp) 3×7.5 15 3×22KVA 4 2×7.5 备注 兼拌砂浆 4 各项施工说明
4.1 装饰架子工程
装饰外架采用双排架,内装饰架采用满堂脚手架,装饰架子横距1.0米,竖距1.8米,步高1.8米,内装饰架竖横距1.8米,步高1.8米。
架子搭设技术要求和基础处理措施:
1、操作层及人行道脚手板必须满铺,板端必须搁置在小横杆上,在同一排横杆上搭接长度应大200mm,严禁出现探头板,脚手板一律采用8#元丝绑扎固定。
2、操作层外侧应设置安全横杆,高度为1200mm,不少于两道钢管,必须与立杆用扣件扣牢。
3、在架子外立杆外侧用聚氯乙烯绿色密目防火安全网封闭,在闸坝外墙的楼层,
4