C、实施项目组合管理过程 D、改进项目组合管理过程 62、()按时间顺序统计被发现缺陷的数量分布。
A、缺陷分布密度 B、缺陷修改质量 C、缺陷趋势分析 D、缺陷存活时间 63、规划质量管理的输入不包含()。
A、质量测量指标B、项目管理计划C、需求文件D、风险登记册
64、()是一种统计方法,用于识别哪些因素会对正在生产的产品或正在开发的流程的特定变量产生影响。
A、过程分析B、实验设计C、标杆对照D、质量审计 65、质量管理实施阶段的工具与技术不包括()。
A、储备分析B、统计抽样C、过程决策程序图D、质量审计 66、67、某项工程的活动明细如下表(时间:周:费用:万元):
项目总预算由原先的60万元增加到63万元,根据上表,在预算约束下该工程最快能完成时间为(66)周,所需项目总费用为(67)万元。 (66)A、9 B、8 C、14 D、12 (67)A、60 B、64 C、56 D、45
68、69某项目由并行的3个活动甲、乙和丙组成,为活动甲分配3人5天可以完成,活动乙分配6人7天可以完成,活动丙分配4人2天可以完成,活动完成后人员可再调配。在此情况下,项目最短工期为( )天,此时人员最少配置为( )。 (68)A、6B、7C、8D、9
(69)A、6B、9C、10D、13
70、某拟建项目财务净现金流量如下表所示,该项目的静态投资回收期是( )年。
A、5.4 B、5.6 C、7.4 D、7.6
71、()is the technology that appears to emulate human performance typicaliy by learning,coming to its own conclusions, appearing to understand complex content, engaging in natural dialogs with people, enhancing human cognittive performance (also known as cognittive computing) or replacing people on execution ofnonroutine tasks. A、Cloud serviceB、Blockchain
C、Internet of thingsD、Artificial intellingence
72、()is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion of the network.
A、Cloud service B、Blockchain
C、Internet of thingsD、Artificial intellingence
73、() includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . Managing the project scope is primarily concerned with defining and controlling
what is not included in the project.
A、Create scopeB、Project stakeholder management C、Preject scope managementD、Project cost management
74、Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().
A、expert judgment B、analogous estimating C、requirements traceability matrix D、three-point estimating
75、() The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies into the project. A、Manage qualityB、Quality auditC、Quality metrics D、Quality improvement
参考答案:
1-5 CBBBD 6-10 ABCAD 11-15 BDAAB 16-20 ACDBC 21-25 BACAD 26-30 ADBDB 31-35 CBADB 36-40 CBCBB 41-45 DBCBB 46-50 DADDC 51-55BBABC 56-60 BBBAA 61-65 ACABA 66-70 AABCC 71-75 DBCCA