Commissioning Procedure for Cold State Air Draught
furnace is -50~-100 Pa, write down the operational parameter. Check the fans and the vibration of the air duct.
6.2.3. Increase the air flow to 50%BMCR、75%BMCR、85%BMCR, keep the negative pressure of the furnace normal, write down the operational parameter. Check the fans and the vibration of the air duct
6.2.4. Keep the air flow is 85%BMCR, increase the main primary air duct pressure to10kPa, check the leakage.
6.2.5. Keep the air flow is 85%BMCR, measure secondary air flow and record secondary air flow and different pressure displayed at DCS. Get flow transducer coefficient by calculation.
6.2.6. Increase the opening of the PAF to 85~95%, measure mill outlet air flow and record the same flow displayed at DCS. Get flow transducer coefficient by calculation. Measure air velocity of mill outlet pipes and measure the same velocity by temporary measuring devices. Get temporary measuring devices coefficient by calculation.
6.2.7. When all jobs shown above have been finished, balance the velocity of the primary air pipes.
6.2.8. Change the opening of the hot/cold dampers, write down the operational parameter.
6.2.9. Change the opening of the second air dampers of the wind boxes, ensure the dampers can work normally.
6.2.10. The commissioning result records are shown in appendix 5.
Page 5 of 14
Commissioning Procedure for Cold State Air Draught
AppendixⅠ Check list of wind box second air dampers
PLTU2 BANTEN-LABUAN (2×300MW)
Unit: System name:Wind box second air dampers Date: items OFA EE E DE D DD CC C BC B AB A AA layer 13 12 11 10 9 8 7 6 5 4 3 2 1 #1 corner #2 corner #3 corner #4 corner Remark:
COMPLETED BY NAME SIGNATURE DATE COMMISSIONING INSTALLATION CHENGDA Page 6 of 14
Commissioning Procedure for Cold State Air Draught
AppendixⅡ Check list of burners and oil guns
PLTU2 BANTEN-LABUAN (2×300MW)
Unit: System name: burners and oil guns Date: NO. Descriptions Burners Installation record Appearance Oil guns and ignitor Installation record Spot-check 1.all ready 2.all data as manufacture Spot-check the dimension after the oil guns and ignitor cutting in 1.all ready 2.circularity as manufacture 3.other data as manufacture 1. no transformation of nozzles 2.all burners are horizontal 3.spot-check some size of nozzles Requirement Result 1 2 Remark: COMPLETED BY NAME SIGNATURE DATE SUBCON CHENGDA Commissioning team PLN Page 7 of 14
Commissioning Procedure for Cold State Air Draught
AppendixⅢ Check list of primary air pipe adjustable orifices
PLTU2 BANTEN-LABUAN (2×300MW)
Unit: System name:Primary air pipe adjustable orifices Date: position A1 A2 A3 A4 B1 B2 B3 B4 C1 C2 C3 C4
COMPLETED BY NAME SIGNATURE DATE COMMISSIONING INSTALLATION CHENGDA Rolling round position D1 D2 D3 D4 E1 E2 E3 E4 / / / / Rolling round Page 8 of 14